Rail firm ‘breaks promise’ on reviving village station

Rail bosses have told 
campaigners they can’t keep a promise to reopen a mothballed East Lothian station next year – because there aren’t enough trains in Scotland.
The old station at East Linton. Picture: Julie BullThe old station at East Linton. Picture: Julie Bull
The old station at East Linton. Picture: Julie Bull

Campaigners say they are “very concerned” after being told by ScotRail that the planned reopening of East Linton station will be delayed by up to two years.

After a long campaign by the Rail Action Group East of Scotland (Rages), returning rail services to East Linton and Reston in the Borders was written into the contract for new ScotRail franchise holder Abellio, which took over the railways in April.

Hide Ad
Hide Ad

The commitment was underlined in November last year, with Scottish Government minister Paul Wheelhouse saying the service could begin as early as December 2016.

However, campaigners have now been told there won’t be enough trains to serve East Linton – which sits on the East Coast Main Line between Dunbar and Drem – until 2018.

Rages spokesman Russell Darling said: “Abellio told us the news recently – we’ve been in touch with the minister for transport to try and sort it out.

“They are quite tight for rolling stock in Scotland, but we thought they might be able to bring something in from elsewhere in Britain.

Hide Ad
Hide Ad

“The minister has said that the reopening is to go ahead, and it’s in Abellio’s franchise.

“We’d be very concerned if services couldn’t be introduced until 2018. We were promised much earlier than that.”

Local MSP Iain Gray, who has taken part in discussions with the government alongside rail campaigners, said the news was a “major disappointment”.

He said: “Getting a proper local service to Dunbar, with a new station at East Linton into the ScotRail franchise, was a massive victory for Rages campaigners.

Hide Ad
Hide Ad

“It is a major disappointment that Abellio are telling us they won’t have the trains to run it until the end of the timescale given, 2018, instead of the earliest date, 2016.”

Both stations were boarded up in the 1960s during sweeping cuts to the UK’s rail network. Campaigners have sought support from an investment fund set up by the Scottish Government to restore and improve train stations and bring East Linton back to life. Design work necessary to 
reopen the station has been estimated to cost £400,000.

A Scottish Government spokesman said: “The Scottish Government remains committed to the delivery of stations and services for East Linton and Reston and will continue to urge all stakeholders to work together to make this happen as soon as is practical.”