HEALTH bosses are having to spend £5.7 million on maintenance, equipment and facilities at the current Sick Kids Hospital and neuroscience centre because of the delay in transferring to the new site.
The new Sick Kids Hospital should have opened in July.The new Sick Kids Hospital should have opened in July.
The new Sick Kids Hospital should have opened in July.

A breakdown of costs also shows the reviews commissioned by Health Secretary Jeane Freeman to establish the extent of the problems at the replacement building cost £500,000.

Ms Freeman ordered a halt to the opening of the £150m new hospital at the beginning of July just days before it was due to open. The move came after last-minute checks found the ventilation system in the critical care unit did not meet national standards. Checks then revealed remedial work was also needed in the water and drainage systems.

Hide Ad
Hide Ad

Now the Sick Kids will have to remain in its current building at Sciennes until next autumn and the Department of Clinical Neurosciences will stay at the Western General Hospital until spring next year.

Health Secretary Jeane Freeman has promised to update MSPs on costs.Health Secretary Jeane Freeman has promised to update MSPs on costs.
Health Secretary Jeane Freeman has promised to update MSPs on costs.

Ms Freeman told MSPs last month that the delay was expected to cost an extra £16 million on top of the £1.35m a month being paid by NHS Lothian to the consortium which built the hospital.

Read More
Call for "heads to roll" over Edinburgh's Sick Kids debacle

Dual running of the two sites will cost £1.5m, while additional maintenance at the current sites is shown as £2m; and additional investment in current facilities and equipment is estimated at £3.7m.

In addition, project team costs are £1.5m; additional project support £550,000; legal, technical and financial fees £300,000; and the independent reviews £500,000.

Hide Ad
Hide Ad

Ms Freeman added: "These estimates will be refined as plans are further developed. I will keep members updates on costs as work proceeds on resolving the current situation."