Edinburgh arena could be delayed until 2029 as project still struggles to secure contractor

Edinburgh’s arena was initially expected to launch in 2027 but has faced delays securing a main contractor

Music lovers could be waiting until the end of this decade before they can see their favourite artists at Edinburgh’s long-promised arena.

The last public update on plans for a 8,500-capacity arena in South Gyle explained in July that the project was facing delays due to rising supply chain costs and an inability to secure a main contractor.

It appears the project has since been hit by further delays with its estimated start date pushed back from this month to May 2027.

AEG Europe hopes to host 150 shows a year at the Edinburgh Park Arena including concerts, comedy shows, boxing and festival showsplaceholder image
AEG Europe hopes to host 150 shows a year at the Edinburgh Park Arena including concerts, comedy shows, boxing and festival shows

An £80 million contract tender shared with the Evening News by construction project analyst Glenigan says the project is due to run for 29 months, which would take it until October 2029.

AEG Europe, which owns venues such as London’s The O2 and Berlin’s Uber Arena, had initially hoped to launch in 2027, but the opening was later rescheduled to 2028.

The company said they were “continuing conversations with various partners” and did not confirm whether the project had been pushed back due to further problems securing a main contractor.

A spokesperson said: “We remain committed to delivering the arena at Edinburgh Park and are continuing to progress the project.

“We hope to have more of an update in 2027.”

The arena will eventually be located behind Edinburgh Park stationplaceholder image
The arena will eventually be located behind Edinburgh Park station | AEG

Planning permission for the city’s first larger indoor concert arena on land behind Edinburgh Park train and tram station was unanimously approved by councillors in June 2024.

If ground is not broken on the project within three years of the full planning permission being granted, permission will lapse and AEG will have to go through the process again.

The Evening News understands that two bidders were recently interested in landing the contract but one has since dropped out, coinciding with the supposed additional delay.

It hopes to host 150 shows each yearplaceholder image
It hopes to host 150 shows each year | AEG

Plans for a large indoor arena in the city were first mooted in 2004, with Forth Ports proposing a venue on land near Ocean terminal in Leith, however the plans never came to fruition.

AEG’s arena with its bigger capacity expects to host 150 shows for an estimated 700,000 visitors each year, creating 250 operational and 700 indirect jobs in the process.