Leith trams: Council wants more money from government

City leaders will ask the Scottish Government for help to foot the bill for a potential £145 million extension of the tram line to Leith.
An artist's impression of a tram en route to Ocean TerminalAn artist's impression of a tram en route to Ocean Terminal
An artist's impression of a tram en route to Ocean Terminal

Cost estimates have been published in an outline business case, which will be tested against quotes provided by construction firms interested in carrying out the work.

Council chiefs said a government grant was one option being considered to help pay for the line, despite the SNP administration’s previous insistence that it would pay “not a penny more” towards the troubled project.

Hide Ad
Hide Ad

The Scottish Government today said it had “no plans” to make a further contribution, but would be willing to discuss the issue with the council.

When the SNP lost a vote at the Scottish Parliament in 2007, forcing the government to provide £500m towards construction of the tram, Finance Secretary John Swinney said: “I’ll contribute the finances the government has said it will contribute, not a penny more, absolutely not a penny more, not even to rescue it.”

However, city transport convener Councillor Lesley Hinds said the city would approach ministers regardless, saying tram projects in England and Ireland had been funded with taxpayers’ cash.

She said: “The Scottish Government have said they would not give any further resources to the Edinburgh Trams, but obviously we would still like to have discussions with them.

Hide Ad
Hide Ad

“If we want to [extend], we need that capital sum, and if you look at most tram projects, such as Dublin, Nottingham, Manchester, the capital funding normally comes from the national government. That’s the normal process.”

Four options have been set out for extending the line, with proposals to take the tram to the foot of Leith Walk, Ocean Terminal and all the way to Newhaven – as originally planned eight years ago.

However, the fourth, extending the line only as far as McDonald Road, has effectively been ruled out as uneconomical.

The report sets out the estimated costs for each of the options, with Newhaven coming with a price tag of £144.7m, while the Ocean Terminal option would cost £126.6m and Leith Walk £78.7m.

Hide Ad
Hide Ad

If the line was fully extended to Newhaven, officials believe it could almost double passenger numbers by 2027, with up to 18.7 million journeys per year.

Based on the tram’s existing business plan, that could boost ticket revenues by up to £17m, helping the service turn a larger operating profit and allowing the city to break even on its investment earlier than the 15 years currently predicted.

Other sources of funding being considered alongside a government grant include EU finance, private investment, or using funds from a City Deal bid being prepared which could unlock billions of pounds of infrastructure investment.

Cllr Hinds added: “I am extremely pleased with the progress of the business case, which already shows the clear economic impact the extension of the tram line could have.

Hide Ad
Hide Ad

“In the tram’s first year of operation we have seen passenger numbers increase, making the case for extending the tram to benefit people elsewhere in the city. But we don’t want to make any rash decisions, and that’s why further due diligence is required.

“We will also be exploring all avenues for funding, and considering a series of new and innovative options to deliver best value. It is essential that we learn from our past mistakes.”

Cllr Hinds pledged that all information gathered during market research and auditing of the business case would be made available to councillors in a “data room”, where they could browse commercially sensitive quotes for “weeks” before any decision was taken.

Councillors will decide which option to take forward in the autumn, but supporters of extension face an uphill battle to convince sceptical SNP members to back the tram.

Hide Ad
Hide Ad

Earlier this year, the party signalled it was willing to put aside long-standing antipathy to the tram if the business case was sound. But a senior SNP source said it could still decide not to back any option if the plan was deemed too expensive.

Conservative transport spokesman Nick Cook questioned the council’s ability to fund any extension.

Cllr Cook said: “Every option being considered involves huge amounts of cash to extend a project considered ‘polarising’, at best, by Edinburgh taxpayers. While it is, of course, sensible to go out and gather as much quality financial information as possible, there is still no escaping the fact the council’s current financial position already casts a long shadow on any potential extension.”

While it is understood the Scottish Government has indicated it would be “happy” to meet with councillors to discuss funding issues, a Scottish Government spokesman said: “Any plan for extending the current Edinburgh tram line is a matter for the council to consider in light of its own funding priorities. We have no plans to make any further contribution, having already had to provide £500m after parliament voted in favour of the project.”

Hide Ad
Hide Ad

The spokesman added that the government was “committed to working with all our cities to unlock investment”.

The options

Foot of Leith Walk

Cost: £78.7m

Cost per km: £40.6m Passengers (2027): 13.6m

Ocean Terminal

Cost: £126.6m

Cost per km: £32.8m Passengers: 17.7m

Newhaven

Cost: £144.7m

Cost per km: £30.9m Passengers: 18.7m

Up to 1200 pipes still to be moved under Leith walk

Leith residents will face considerable disruption in any tram extension, with city officials revealing that hundreds of underground pipes and cables could still have to be moved. Despite years of works to divert water and gas mains as part of the original tram construction project, up to 1200 potential obstacles still sit beneath Leith Walk, with the majority of them likely needing to be moved.

Transport convener Councillor Lesley Hinds said she was “surprised” the figure was so high despite previous works, but said it was important that the city approached any extension plan with caution and anticipated possible problems.