The five-month programme of works will begin at the end of October and run until March next year
Edinburgh Council has announced a timeline for long-waited pavement upgrades on Morningside Road.
The works, which include a widening of the pavement opposite Waitrose as well as resurfacing and improvements to pedestrian crossings, will begin on Monday, October 26 and are scheduled to be completed by March next year.
The improvements will see the temporary “covid bollards” on the west side of Morningside Road opposite Waitrose removed, and replaced with a widened pavement.


The signal-controlled pedestrian crossing outside Waitrose is also set to be renewed, while resurfacing works are planned for sections of Falcon Road and Falcon Road West.
Temporary road closures and diversions required to facilitate the works are expected to be announced in the coming weeks.
David Hunter, Convener of the Living Streets Edinburgh Group, said: “Morningside Road has some dreadfully narrow pavements which are far below the minimum that the council aspires to for local high streets.
“It's good to see the temporary 'covid bollards' go at last, to be replaced by a proper pavement. However, it's a pity that there's no plan to give pedestrians more space at the Health Centre.”
A spokesperson for Edinburgh Council said: “Ahead of the work starting our contractor will be in touch with more information, including details of temporary road closures, diversions, parking changes and access to properties and local businesses.
“While there are clear long-term benefits of improving pavements and crossings, we do appreciate that there will be disruption during the works. This is necessary to make sure we can complete the work safely and efficiently.
“We thank you in advance for your patience and support. Alongside our contractor, we will make every effort to keep disruption to a minimum.”


What’s the timeline for improvements?
Here’s the current schedule for the proposed works:
Steel’s Place at Morningside Road - October 26 until December 11
- Introduction of a continuous pavement on Steel’s Place at Morningside Road
- Renewal and upgrading of the signal-controlled pedestrian crossing of Morningside Road near Steel’s Place
Falcon Road/ Falcon Road West - from December 6 until December 23 2026
- Renewing the road surface of Falcon Road West and Falcon Road between Falcon Avenue and Falcon Road West
Morningside Road at Waitrose - February 1 until March 31 2027
- Upgrading of the widened pavement on the western side of Morningside Road from Cuddy Lane to The Merlin access
- Renewal and upgrading of the signal-controlled pedestrian crossing of Morningside Road at Waitrose