Edinburgh A71 Dalmahoy junction improvement faces new delay

The long-awaited upgrade of the Dalmahoy junction on the A71 outside Edinburgh is facing yet another delay.

It's 40 years since residents first called for improvements at the danger spot and more than three years since a fully-signalised junction was given the go-ahead.

Locals have repeatedly been told work would start soon on the £1.6 million project, but the purchase of some land needed for the new junction was held up by the death of one of the landowners.

A full upgrade of the dangerous Dalmahoy junction on the A71 outside Edinburgh was finally approved in 2022 - but work has yet to start.placeholder image
A full upgrade of the dangerous Dalmahoy junction on the A71 outside Edinburgh was finally approved in 2022 - but work has yet to start.

And now the need to revise the design of the drainage at the site means there will be a further three-month delay.

Edinburgh transport convener Stephen Jenkinson, who is also one of the councillors for the area, said he was disappointed when he was given this new update and has told officials he wants the scheme completed by the end of the calendar year.

He said: "The land purchase has now all been completed. But now they have been able to do more substantial surveys on the land, the initial drainage drawings require more work.

"In the next couple of weeks they're going to appoint an external consultant to do that, but it is quite complex. It will take 12 weeks to get them back."

He said once the drawings had been received, the project should be ready to go out to contract and it was expected to take six weeks to build the junction.

The campaign for traffic lights at the Dalmahoy junction dates back to 1986, when the community council made the first request. In 2015 a council report concluded a fully-signalised junction was the only practical option to improve safety.

But after delays and rising costs, the transport committee voted in 2021 to scale back the project and install only a pedestrian crossing. That decision was reversed after Labour won control in 2022 and gave the go-ahead for a fully-signalised junction.

But the residents are still waiting for work to start.

Cllr Jenkinson said: "I've expressed my disappointment at the length of time it has taken to do this project. And I have said my expectation is that it will be delivered within this calendar year.

"The junction is not getting any safer, the condition of the road is getting worse and every year this doesn't get delivered, it gets more expensive."