Leith Street to close AGAIN this week as work continues on St James Development
The road is set to be closed between Princes Street and Greenside Row from 7pm on Thursday, June 6 until 7am on Tuesday, June 11.
It is understood the road will be closed to motorists to allow contractors Laing O'Rourke to install a large mobile crane.
Advertisement
Hide AdAdvertisement
Hide AdRoyal Terrace, Easter road, Calton Road and George Street will also be affected by temporary traffic restrictions for the same period of time.
This isn't the first time that Leith Street has closed recently in relation to the building work at St James Development.
It was closed to motorists for three weeks in May to enable a crane lift.
While erected, the crane gave spectacular 360 degree views over the city, which you can see a video of here.
Advertisement
Hide AdAdvertisement
Hide AdA spokesperson for Laing O'Rourke said: "Leith Street will need to close temporarily to allow the installation of a large mobile crane that requires the full width of Leith Street, to allow the install of large structural steelwork sections.
"The road will be closed from 7pm on 6th June until 7am on 11 June."