Edinburgh has a host of major transport projects in the pipeline, some where preparations have just started, others well advanced and some nearly ready to go.
Here are details of the top 21 projects, as prioritised by the transport committee last year, including what they are about, how much they are expected to cost and, crucially, what stage they are at.
Their priority ranking does not, however, indicate how soon they will be realised.
Transport convener Stephen Jenkinson says the council always needs to have projects at different stages of development in order to secure the money required.
He said: "A lot of these projects are externally funded - either from the [Scottish Government's] Active Travel Investment Fund or the Bus Infrastructure Fund, two big pots of money.
"But you have to have projects at the right stage of development in order to access the money. Across our 2025/26 programme, the council levered in about £14.2m of Scottish Government funding to help us deliver these projects."
The council's transport and environment committee will be asked to approve the list of projects this week.

1. Bridges corridor
Development of proposals for the North Bridge / South Bridge corridor and associated streets, restricting through traffic except for buses and prioritising walking and wheeling. Cost band: £10-30m. Stage: 1 - Preparation and brief. Ranking: joint 1. | TSPL Photo: Lisa Ferguson

2. Cowgate corridor
Development of proposals for the Cowgate corridor and associated streets, restricting through traffic except for buses and prioritising walking and wheeling. Cost band: £10-30m. Stage: 1 - Preparation and brief. Ranking: joint 1. | Iconic Media

3. St Andrew Square
Active travel connection from George Street to CCWEL on North St David Street. Cost band: £1-3m. Stage: 2 - Concept design. Ranking: 3. | TSPL

4. Meadows to George Street
New cycleways and widened footways from the Meadows to Forrest Rd along George IV Bridge and down The Mound to Hanover Street, finishing at George Street. Cost band: £10-30m. Stage: 3 - Developed design. Ranking: joint 4. | Edinburgh City Council